To shorten project duration, resources have been added to tasks on the critical path. The plan should then be reviewed for the __________.

A.
Lagging time on other paths
B.
Emergence of a new critical path
C.
Resource assigned to other tasks on the critical path
D.
Longest task remaining in the plan
I agree with the answer. B