A contingency plan is ________.

A.
A planned response that defines the steps to be taken, if an identified risk event should occur
B.
A workaround
C.
A reserve used to allow for future situations which may be planned for only in part
D.
All of the above
Explanation:
A planned response that defines the steps to be taken, if an identified risk event should occur is called contingency plan
Correct answer is A
0
0
Inputs to the Collect Requirements process include the:
a. Project scope statement, work breakdown structure, and scope management plan.
b. Project management plan, enterprise environmental report, and organizational process assets.
c. Requirements management plan, project charter, and stakeholder register.
d. Scope management plan, requirements management plan, and project scope statement.
The answer is: c
0
0
Change request disposition (status updates) are an output of which process?
a. Close Project or Phase.
b. Direct and Manage Project Execution.
c. Perform Integrated Change Control.
d. Monitor and Control Project Work.
The answer is: c
0
0
The ____________________________ process identifies specific actions to be performed to produce project deliverables.
a. Sequence Activities
b. Define Activities
c. Plan Schedule Management
d. Define Scope
The answer is: b
0
0
Which estimating uses a statistical relationship between historical data and other variables to calculate an estimate for activity parameters?
a. Analogous estimating
b. Rolling wave planning
c. Parametric estimating
d. Precedencediagrammingmethod
The answer is: c
0
0