PrepAway - Latest Free Exam Questions & Answers

This process is known as ________.

Customer formally accepts the deliverables of each project phase. This process is known as ________.

PrepAway - Latest Free Exam Questions & Answers

A.
Verify Scope

B.
Quality Assurance

C.
Quality Control

D.
Quality Measurement

Explanation:
Verify Scope is the process of formally accepting the deliverable of a project or phase. A is incorrect because EVM measures project performance. C is incorrect because quality control is concerned with the correctness of the work, not the acceptance of the work. QA is incorrect because this described the quality program for the organization as a whole.

One Comment on “This process is known as ________.


Leave a Reply