A vRealize Automation Tenant Administrator has identified a virtual machine with low resource utilization. The
owner has been given 5 days to respond to the reclamation request. The blueprint used to build the virtual
machine has an archive period of 10 days and there are 21 days left in the original machine lease.
If the owner responds today confirming the virtual machine is no longer needed, how many days will elapse
before the virtual machine is destroyed?
A.
10 days
B.
31 days
C.
21 days
D.
Today
Correct answer is A.
If the machine owner approves the reclamation request, the machine lease will instantly expire. If there is an archive period set, the machine will only be switched off and will be deleted at a later time, as per policy. Otherwise, its resources will be released immediately.
https://cloudadvisors.net/chapter-15-reclamations/