The responsibilities of a disaster recovery relocation team include:

The responsibilities of a disaster recovery relocation team include:

PrepAway - Latest Free Exam Questions & Answers

A.
obtaining, packaging and shipping media and records to the recovery facilities, as well as establishing and overseeing an offsite storage schedule.

B.
locating a recovery site, if one has not been predetermined, and coordinating the transport of company employees to the recovery site.

C.
managing the relocation project and conducting a more detailed assessment of the damage to the facilities and equipment.

D.
coordinating the process of moving from the hot site to a new location or to the restored original location.

Explanation:
Choice A describes an offsite storage team, choice B defines a transportation team and choice C defines a salvage team.