PrepAway - Latest Free Exam Questions & Answers

Which of the following risks could result from inadequate software baselining?

Which of the following risks could result from inadequate software baselining?

PrepAway - Latest Free Exam Questions & Answers

A.
Scope creep

B.
Sign-off delays

C.
Software integrity violations

D.
inadequate controls

Explanation:
A software baseline is the cut-off point in the design and development of a system beyond which additional requirements or modifications to the design do not or cannot occur without undergoing formal strict procedures for approval based on a businesscost -benefit analysis. Failure to adequately manage the requirements of a system through baselining can result in a number of risks. Foremost among these risks is scope creep, the process through which requirements change during development. ChoicesB , C and D may not always result, but choice A is inevitable.