After implementation of a disaster recovery plan, pre-disaster and post-disaster operational costs for an organization will:

PrepAway - Latest Free Exam Questions & Answers

A.
decrease.

B.
not change (remain the same).

C.
increase.

D.
increase or decrease depending upon the nature of the business.

Explanation:
There are costs associated with all activities and disaster recovery planning (DRP) is not an exception. Although there are costs associated with a disaster recovery plan, there are unknown costs that are incurred if a disaster recovery plan is not implemented.