PrepAway - Latest Free Exam Questions & Answers

The MAJOR concern for an IS auditor reviewing the project is that there will be:

During the development of an application, the quality assurance testing and user acceptance testing were combined. The MAJOR concern for an IS auditor reviewing the project is that there will be:

PrepAway - Latest Free Exam Questions & Answers

A.
increased maintenance.

B.
improper documentation of testing.

C.
inadequate functional testing.

D.
delays in problem resolution.

Explanation:
The major risk of combining quality assurance testing and user acceptance testing is that functional testing may be inadequate. Choices A, B and D are not as important.

One Comment on “The MAJOR concern for an IS auditor reviewing the project is that there will be:


Leave a Reply