An organization has a recovery time objective (RTO) equal to zero and a recovery point objective (RPO) close to 1 minute for a critical system. This implies that the system can tolerate:

PrepAway - Latest Free Exam Questions & Answers

A.
a data loss of up to 1 minute, but the processing must be continuous.

B.
a 1-minute processing interruption but cannot tolerate any data loss.

C.
a processing interruption of 1 minute or more.

D.
both a data loss and a processing interruption longer than 1 minute.

Explanation:
The recovery time objective (RTO) measures an organization’s tolerance for downtime and the recovery point objective (RPO) measures how much data loss can be accepted. Choices B, C and D are incorrect since they exceed the RTO limits set by the scenario.