What is the LEAST likely cause of the slippage?

The Java development of a project is outsourced to India. The project schedule is starting to slip.
What is the LEAST likely cause of the slippage?

PrepAway - Latest Free Exam Questions & Answers

A.
Lack of competent programmers

B.
Cultural influences

C.
Internationalization

D.
Communication