In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project

In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.

PrepAway - Latest Free Exam Questions & Answers

A.
Increase, increase

B.
Decrease, decrease.

C.
Increase, decrease.

D.
Increase, increase or decrease.

E.
Decrease, increase.