Taking this new dependency into account, what would be the effect on the project?

Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

PrepAway - Latest Free Exam Questions & Answers

A.
It would increase the critical path.

B.
Communication would be more complex.

C.
There would be no effect.

D.
It would delay activity F.