Project scope statement and resource calendars are inputs to what Project Time Management process?
A. Activity Sequencing
B. Activity Resource Estimating
C. Schedule Development
D. Schedule Control
One Comment on “Project scope statement and resource calendars are inputs to what Project Time Management process?”
Alexandersays:
The answers are B and C.
“6.5 Estimate Activity Durations” and “6.6 Develop Schedule” have as an input: Project scope statement and resource calendars.
The answers are B and C.
“6.5 Estimate Activity Durations” and “6.6 Develop Schedule” have as an input: Project scope statement and resource calendars.