Using the chart, what is the lowest cost of crashing this project to save four weeks?

Using the chart, what is the lowest cost of crashing this project to save four weeks?

PrepAway - Latest Free Exam Questions & Answers

A.
$18,000

B.
$6,000

C.
$7,000

D.
$9,000