Given the following values, what is the calculated expected activity cost (CE) when using PERT?

Given the following values, what is the calculated expected activity cost (CE) when using PERT?

CO = $7,000

CM = $10,500

CP = $11,000

PrepAway - Latest Free Exam Questions & Answers

A.
$ 4,750

B.
$ 9,500

C.
$10,000

D.
$11,500


Leave a Reply