What are the performance measurements for the Schedule Control process?
A.
SV (EV – PV) and SPI (EV � PV)
B.
SV (PV – EV) and SPI (PV � EV)
C.
SV (EV – BAC) and SPI (EV � BAC)
D.
SV (EV – AC) and SPI (EV � AC)
Explanation:
Schedule variance is (EV – PV) and schedule performance index is (EV PV).