Which of the following is an input to Direct and Manage Project Execution?
A.Requested changes
B.Approved change requests
C.Work per
formance information
D.Implemented defect repair
Which of the following is an input to Direct and Manage Project Execution?
A.Requested changes
B.Approved change requests
C.Work per
formance information
D.Implemented defect repair
You must be logged in to post a comment.
Which of the following is an input to Direct and Manage Project Execution?
A.Performance reports
B.Project charter
C.Outputs from planning processes
D.Enterprise environmental factors
You must be logged in to post a comment.