The process of confirming human resource availability and obtaining the team necessa…

The process of confirming human resource availability and obtaining the team necessa

ry to complete project activities is known as:

A. Plan Human Resource Management.

B. Acquire Project Team.

C. Manage Project Team.

D. Develop Project Team.