The scope management plan and scope baseline are contained in:
A.organizational process assets
B.a requirements traceability matrix
C.the project charter
D.the project management plan
Ans
The scope management plan and scope baseline are contained in:
A.organizational process assets
B.a requirements traceability matrix
C.the project charter
D.the project management plan