The zero duration of milesto
nes in project planning occurs because milestones:
A.Are unpredictable and challenge the Plan Schedule Management process.
B.Occur at random times in the project plans.
C.Represent a moment in time such as a significant project point or event.
D.Represent
both significant and insignificant points in the project and are difficult to anticipate.