Scope, schedule, and cost parameters are integrated in
the:
A. Performance measurement baseline.
B. Analysis of project forecasts,
C. Summary of changes approved in a period,
D. Analysis of past performance.
Scope, schedule, and cost parameters are integrated in
the:
A. Performance measurement baseline.
B. Analysis of project forecasts,
C. Summary of changes approved in a period,
D. Analysis of past performance.
You must be logged in to post a comment.