When a backward pass is calculated from a schedule constraint that is later than the early finish date that ha

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A. Negative

B. Zero

C. Positive

D. Free