The risk response strategy in which the project team acts to reduce the probability of occurrence or impa
ct of a risk is known as:
A.exploit
B.avoid
C.mitigate
D.share
The risk response strategy in which the project team acts to reduce the probability of occurrence or impa
ct of a risk is known as:
A.exploit
B.avoid
C.mitigate
D.share