When
cost variance is negative and schedule variance is positive, the project is:
A.under budget and behind schedule.
B.over budget and ahead of schedule.
C.on schedule.
D.complete; all planned values have been earned.
When
cost variance is negative and schedule variance is positive, the project is:
A.under budget and behind schedule.
B.over budget and ahead of schedule.
C.on schedule.
D.complete; all planned values have been earned.
You must be logged in to post a comment.