A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value
of the work completed to date?
A.US$S000
B.US$9500
C.US$10,000
D.US$12,500
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value
of the work completed to date?
A.US$S000
B.US$9500
C.US$10,000
D.US$12,500
You must be logged in to post a comment.