Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communi

Who is responsible for ensuring that Communication Management Strategy is appropriate and that
planned communication activities actually take place?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Assurance

B.
Project Manager

C.
Corporate or Programme Management

D.
Project Support