PrepAway - Latest Free Exam Questions & Answers

Which of the following management products ARE updated as part of Managing a stage boundary?

Which of the following management products ARE updated as part of Managing a stage
boundary?
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief

PrepAway - Latest Free Exam Questions & Answers

A.
1, 2, 3

B.
1, 3, 4

C.
1, 2, 4

D.
2, 3, 4

4 Comments on “Which of the following management products ARE updated as part of Managing a stage boundary?

  1. Jamal says:

    project brief is created in the SU process, it is not logical to update that in the MB process. If you don’t understand this then you should read again the SU process chapter and check appendix a.




    0



    0

Leave a Reply