Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

PrepAway - Latest Free Exam Questions & Answers

A.
Review the stage status

B.
Review work package status

C.
Report Highlights

D.
Take corrective action