which strategy would the change control process be recorded?

In which strategy would the change control process be recorded?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality Management Strategy

B.
Configuration Management Strategy

C.
Risk Management Strategy

D.
Communication Management Strategy