Which of the following activities could trigger the production of an exception plan?

Which of the following activities could trigger the production of an exception plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Review Stage status

B.
Giving ad hoc direction

C.
Escalating a project issue

D.
Report stage end