If the Project Board are too busy to authorize all change requests themselves they can appoint?
A. A Change Authority
B. A Change Board
C. A Change Committee
D. A Change Budget
3 Comments on “If the Project Board are too busy to authorize all change requests themselves they can appoint?”
Lulzsays:
Answer is A
3
0
ksays:
A
The Project Board may delegate authority for
approving responses to requests for change or offspecifications to a separate individual or group,
called a Change Authority
Answer is A
3
0
A
The Project Board may delegate authority for
approving responses to requests for change or offspecifications to a separate individual or group,
called a Change Authority