Which statement best explains the purpose of Tailor to suit the project environment?

A.
Ensure project controls are based on project’s scale, complexity, importance, capability and risk
B.
To use a set of pre-defined templates for the size of project
C.
To tailor the use of the principles to suit the project
D.
To pick which PRINCE2 processes to apply and which to leave out
Incorrect answer.
The correct answer is A (not D)
See, “Managing Successful Projects with Prince2” (2009)
Section 19, 19.1, page 215, “What is tailoring”