Which of the following is NOT an objective of Initiating a Project?

A.
Understanding the scope of what is to be done and the products to be delivered
B.
Understanding the roles and responsibilities of the Project Management Team
C.
Understand how quality required will be achieved
D.
Understand how progress will be monitored and controlled
I have the same idea. B