The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and
Quality are three of them, what are the other three?

A.
Scope, People & Resources, Benefit
B.
Scope, Risk, Product
C.
Risk, Benefit, Product
D.
Scope, Risk, Benefit
Incorrect answer.
The correct answer is D, “Scope, Risk, Benefit” (not A)
See, “Managing Successful Projects with Prince2” (2009)
P102, Table 10.1, this shows the six areas of tolerance