Which of the following management products ARE updated as part of Managing a stage boundary? 1. Business Case 2. Benefits Review Plan 3. Configuration Item Records 4. Project Brief
A. 1, 2, 3
B. 1, 3, 4
C. 1, 2, 4
D. 2, 3, 4
4 Comments on “Which of the following management products ARE updated as part of Managing a stage boundary?”
networkmanagers says:
I agree with the answer. A
2
0
Jamalsays:
project brief is created in the SU process, it is not logical to update that in the MB process. If you don’t understand this then you should read again the SU process chapter and check appendix a.
I agree with the answer. A
2
0
project brief is created in the SU process, it is not logical to update that in the MB process. If you don’t understand this then you should read again the SU process chapter and check appendix a.
0
0
which answer is it??
0
0
A
1
0