PrepAway - Latest Free Exam Questions & Answers

Which IBM Maximo Asset Management functionality will meet this requirement?

A customer requires that all completed work orders are to be closed 30 days after completion. Which IBM Maximo Asset Management functionality will meet this requirement?

PrepAway - Latest Free Exam Questions & Answers

A.
Send e-mail.

B.
Set up acron task.

C.
Set up an escalation.

D.
Set the number of days under organization’s work order options.

Explanation:
12 IBM 000-001: Practice Exam


Leave a Reply