What will happen to associated preventive maintenance (PM) records when an asset is decommissioned?

What will happen to associated preventive maintenance (PM) records when an asset is decommissioned?

PrepAway - Latest Free Exam Questions & Answers

A.
There is no automatic method to change the PM(s) status to INACTIVE.

B.
The PM(s) will become in INACTIVE if ‘Change the Status of All Associated PM(s) to Inactive?’ is checked while decommissioning the asset.

C.
The only way to change the status of the PM(s) to INACTIVE is to remove the assets from the PM(s) and then change the status of the PM(s) to INACTIVE.

D.
If the ‘Change the Status of All Associated PM(s) to Inactive?’ is not selected during decommissioning, the PM(s) status will remain ACTIVE; however, work order cannot be generated from the PM having a decommissioned asset.