Which statement is true regarding this scenario?

A team estimates a Story using the Planning Poker technique. The team decides to allocate
five Story points to the Story, because the Developers estimated two points and the Testers
estimated three points.
Which statement is true regarding this scenario?

PrepAway - Latest Free Exam Questions & Answers

A.
Points are assigned by the Scrum Master, not by the team.

B.
Points are assigned for the overall Story, not for parts of the Story.

C.
Points are never estimated, but always determined beforehand.

D.
The team forgets to ask the Product Owner about the estimate.