What is the relationship between the Product Backlog, the Release Backlog and the Sprint Backlog?

What is the relationship between the Product Backlog, the Release Backlog and the Sprint
Backlog?

PrepAway - Latest Free Exam Questions & Answers

A.
The Product Backlog is a subset of the Sprint Backlog, which is a subset of the Release
Backlog.

B.
The Release Backlog is a subset of the Product Backlog, which is a subset of the Sprint
Backlog

C.
The Sprint Backlog is a subset of the Product Backlog, which is a subset of the Release
Backlog.