What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level o

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working
at its peak level of productivity?

PrepAway - Latest Free Exam Questions & Answers

A.
Keeping high priority features at the top of the Product Backlog.

B.
Not allowing changes to the Product Backlog once the Sprint begins.

C.
Supporting the team’s decisions and resolving the team’s issues.