What would be the elapsed time required to complete the Story?

A user story was estimated at five ideal hours. On a normal eight hour working day, the team
gets about four hours of actual work time.
What would be the elapsed time required to complete the Story?

PrepAway - Latest Free Exam Questions & Answers

A.
One day and two hours

B.
Two days

C.
Five hours