What is the best course of action for the team?

Near the end of a Sprint, the team realizes that they will not be able to complete the stories
they had committed to.
What is the best course of action for the team?

PrepAway - Latest Free Exam Questions & Answers

A.
Add resources and team members to meet the goals of the current Sprint.

B.
Ask the Product Owner to decide which stories can be delayed until the next Sprint.

C.
Decide on a new definition of ‘done’ for the Sprint Backlog Items.