A story was estimated at eight ideal hours. A working day is eight hours. Developers can get
about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?

A.
1.25 days
B.
1.33 days
C.
2 days
D.
This cannot be determined without knowing the velocity.