You are the project manager for your organization. You have identified a risk event you’re your
organization could manage internally or externally. If you manage the event internally it will cost
your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can
manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the
solution is in use. How many months will you need to use the solution to pay for the internal
solution in comparison to the vendor’s solution?

A.
Approximately 8 months
B.
Approximately 15 months
C.
Approximately 13 months
D.
Approximately 11 months