You are the project manager for BlueWell Inc. You are reviewing the risk register for your project.
The risk register provides much information to you, the project manager and to the project team
during the risk response planning. All of the following are included in the risk register except for
which item?

PrepAway - Latest Free Exam Questions & Answers

A.
Network diagram analysis of critical path activities

B.
Symptoms and warning signs of risks

C.
List of potential risk responses

D.
Trends in qualitative risk analysis results