PrepAway - Latest Free Exam Questions & Answers

What approach can a project manager use to improve the project’s performance during qualitative risk ana

What approach can a project manager use to improve the project’s performance during qualitative
risk analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
Focus on near-term risks first.

B.
Create a risk breakdown structure and delegate the risk analysis to the appropriate project team
members.

C.
Focus on high-priority risks.

D.
Analyze as many risks as possible regardless of who initiated the risk event.


Leave a Reply