What risk response has Linda used in this instance?

Linda is the project manager of the NAB Project. One of the risks her project team has identified is
too dangerous for the project team to manage internally so she has hired a vendor to complete
this portion of the project and to manage the identified risk. What risk response has Linda used in
this instance?

PrepAway - Latest Free Exam Questions & Answers

A.
Transference

B.
Avoidance

C.
Contractual

D.
Mitigation