Which one of the following is the best explanation for completing qualitative risk analysis?

David is the project manager of HGF project for his company. David, the project team, and several
key stakeholders have completed risk identification and are ready to move into qualitative risk
analysis. Tracy, a project team member, does not understand why they need to complete
qualitative risk analysis. Which one of the following is the best explanation for completing
qualitative risk analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
It is a cost-effective means of establishing probability and impact for the project risks.

B.
Qualitative risk analysis helps segment the project risks, create a risk breakdown structure, and
create fast and accurate risk responses.

C.
All risks must pass through quantitative risk analysis before qualitative risk analysis.

D.
It is a rapid and cost-effective means of establishing priorities for the plan risk responses and
lays the foundation for quantitative analysis.