PrepAway - Latest Free Exam Questions & Answers

How much detail and repetition in approach for risks to be reassessed for probability and impact?

Your organization, as part of its enterprise environmental factors, has established risk governance
to be implemented in each project. Part of this governance is the reassessment of risks within
each project. How much detail and repetition in approach for risks to be reassessed for probability
and impact?

PrepAway - Latest Free Exam Questions & Answers

A.
Each risk reassessment should go into the same depth as the original risk assessment activity.

B.
The probability and impact of risk event should determine the level of reassessment throughout
the project lifecycle.

C.
The amount of detail of repetition that is appropriate depends on how the project progresses
relative to its objectives.

D.
The level of detail and reassessment should reflect the priority of the project.


Leave a Reply