What is the only output of the quantitative risk analysis process?

You are the project manager of the NKQ project for your organization. You have completed the
quantitative risk analysis process for this portion of the project. What is the only output of the
quantitative risk analysis process?

PrepAway - Latest Free Exam Questions & Answers

A.
Probability of reaching project objectives

B.
Risk register updates

C.
Risk response

D.
Risk contingency reserve